Step-By-Step Guide

1.Changing the view to ‘Horizontal view’ makes it easier to reschedule tasks in the next shift. Simply go to the ‘Display Options’, click ‘Process Plan’ then choose ‘Horizontal View’. This will make the Day and Night shifts next to each other. Simply drag the tasks to be rescheduled to the next shift.

2.Rescheduling multiple tasks can be done by holding CTRL, select multiple tasks then drag to next shift. If you want to reschedule duplicates of the tasks, hold the CRTL whilst dragging to the next shift.

3.If the task will be rescheduled across several days, drag the task into the Planned task section, then go to the preferred date and shift then schedule the task again.