Step-By-Step Guide
1. Go to the scheduler screen.
2. Schedule a task or select an existing scheduled task.
3. From the end corner of the task, drag until the required date and shift the task is to be scheduled. A prompt will show up confirming the task split.
4. Click Yes and this will automatically split and link the tasks.
5. If the task will be split in two shifts, hover over into the task then click the ‘Split the task in half’ button.
Limitations
Split tasks cannot be imported. Needs to be done manually.
Links are automatically created; hence, this can't be deleted to manage the tasks individually.
Split tasks are not linked in the database (user can't identify when the group of tasks belong to the same sequence).
Advantages of Split tasks Vs Multi-Shift tasks
Tasks can be rescheduled by dragging task/s across the shifts.
Tasks can be duplicated, edited, deleted the same way than with other tasks.