A Standard Task functions like a stamp that users can schedule repeatedly for different shifts. CiteOps allows planners and schedulers to plan Standard Tasks in the future (up to 5 weeks in advance) by the Week 3, 4 and 5 schedules.
This guide explains how you can accomplish this.
Step-By-Step Guide
Follow these steps to add Standard Tasks to the "Week 3, 4, and 5" schedule in CiteOps.
1. Click on the Planning Board icon.
2. Click on Weeks 3, 4 and 5.
3. Drag and drop the Standard Task into the desired Process, Shift and weeks.
4. The task will appear in the adequate Process, Shift and Week.
5. Right-click on the task to edit, delete or choose one of the options from the hamburger menu.